Technical Requirements for Refractory Castable Construction

The production process of refractory castable is simple, labor-saving, and energy-saving, with high construction efficiency and good quality. It can be prepared on site or materials with excellent performance can be selected as needed. Therefore, refractory castable is an unshaped refractory material that is used in large quantities and has a wide range of applications in furnace construction projects.

Construction Requirements

1. Mixing of refractory castables should use water.

2. The formwork used for casting should have enough rigidity and strength, the size should be accurate, and deformation should be prevented during construction. The joints of the formwork should be tight with no slurry leakage, and anti-adhesion measures should be taken. The surface of heat preservation masonry in contact with the casting material shall take waterproof measures.

3. The castables are mixed by a forced mixer. The mixing time and the amount of liquid added should follow the construction instructions. When replacing the material grade, the mixer, hopper, and weighing container should be cleaned.

4. Mixed refractory castables should be poured within 30 minutes or according to the time specified in the construction instructions. The first set of castables should not be used.

Expansion Joints and Continuous Pouring

5. Continuous casting refractory furnace lining expansion joints should be set in accordance with the design provisions. Where no provision is given, the average value of expansion joints per meter of lining can be used as follows: clay refractory castables for 4-6 mm, high alumina cement refractory castables for 6-8 mm, phosphate refractory castables for 6-8 mm, water glass refractory castables for 4-6 mm, and silicate cement refractory castables for 5-8 mm.

6. Refractory castable casting should be continuous. Before the first layer of pouring material sets, the second layer of pouring material should be completed; if the interval exceeds the setting time, the construction joint should be dealt with according to the requirements. Construction joints should be left on the center line of the same row of anchor bricks.

Curing, Mold Removal and Quality Control

7. After the construction of refractory castable is finished, it should be maintained according to the method specified in the design. Curing shall not be subject to external forces and vibration.

8. Mold removal: the non-load-bearing formwork can be dismantled only when the strength of the castable can ensure that its surface and corners are not damaged or deformed due to removal of the formwork. The load-bearing formwork can be removed only after the castable reaches 70 percent of the design strength. Thermosetting castables should be baked to the specified temperature before removal.

9. The cast lining surface shall not have defects such as skinning, cracks, and holes. Slight grid cracks are allowed.

10. The prefabricated parts of refractory castables should not be stacked in the open. When stacked in the open air, rainproof and moistureproof measures should be taken.

Frequently Asked Questions

How quickly should mixed castable be poured? Within 30 minutes or according to the construction instructions; the first set of castables should not be used.

When can load-bearing formwork be removed? Only after the castable reaches 70 percent of the design strength.

What expansion joint values are typical? about 4-6 mm per meter for clay and water glass castables, and 6-8 mm for high alumina cement and phosphate castables.

Why must formwork joints be tight when casting refractory castable? The joints of the formwork should be tight with no slurry leakage, anti-adhesion measures should be taken, and the surface of heat preservation masonry in contact with the casting material should take waterproof measures.

How should the mixer be handled when changing castable grade? When replacing the material grade, the mixer, hopper, and weighing container should be cleaned, and the mixing time and the amount of liquid added should follow the construction instructions.